Tuesday, November 15, 2011 By Ashton Cane
-
Advertising
What's Happening Now:
As elements of the building reach completion, new work will be started including external metal framing, glass and window framing, and roofing. With so much being done, Relocation Coordinator Ms. Newell wants to point out the hard work of the over 200 construction workers and contractors, who are making the Jewel of Burtonsville sparkle.
What to Expect Soon: Despite the Jewel of Burtonsville being behind schedule by approximately 46 days, we can still expect to see a great deal of progress made in the next four weeks. Work on the new building will consist of geothermal tie-ins, masonry enclosures, internal metal framing, internal tile, ceiling panels.
Approximately 189 Days
|